Starwood has been building our house for over a year, and it's only 3200 square feet. They did not estimate costs correctly and so far we have paid more than $44,200 out-of-pocket for items that went over budget--even though we told them in great detail ahead of time exactly what we wanted; they just didn't research the actual cost of items. Starwood does not have their own subcontractors and hires independent subcontractors for each portion of the work. Many builders work this way, but this has caused huge gaps in work getting done, and many days no one is working on the house at all. Our project manager seems disorganized at times and he and/or subcontractors have made changes to the house without asking us. Our house was originally supposed to be done in October 2017; now it's February 2018. But with the amount of work left and the very, very slow pace of progress, I'll be surprised if we meet that date.